Huffman High School - Concrete
Tuesday, December 28, 2010
A Slab
Building A is ready for the slab pour. Now we just need a break in the weather to pour it.
Thursday, December 23, 2010
B 3rd pour
We started pouring at 5am and poured the rest of B and a couple thousand feet in A
Wednesday, December 22, 2010
Prepping our 3rd slab pour in B and some in A.
Tuesday, December 21, 2010
B second slab pour
Stone base is being applied to the kitchen area and rooms around it.
Monday, December 20, 2010
B 2nd slab pour
We started pouring the second slab pour at 5:15am this morning.
We are countinuing footers in C building
2nd pour was about 14,100 sq' and took 205 yards of concrete.
Tuesday, December 14, 2010
We started footings in C area today
Laying gravel in B pour 2 area
2" depressed slab in area B 2nd pour
We have a few more footings in A to pour
Monday, December 13, 2010
We are spreading gravel to prep te second slab pour in area B.
Blankets were placed on the slab to keep it from freezing over the weekend.