Saturday, December 11, 2010

Slab Pour #1

We were able to start cutting the control joints in the slab around 1pm today. FF 51 & FL 39
7:30am the finishers are still working on finishing the concrete.


Friday, December 10, 2010

Area B 1st Slab pour

We poured the first slab in area B today. We poured 144 cubic yards starting at 7:30am and finished about 10:15am.


Wednesday, December 8, 2010

Interior footings in B area.

Using the conveyor truck we were able to install stone in about 85% of the first pour in B.


The elevator pit is being waterproofed, this should only take a few hours, then we can back-fill and prep for the slab pour.


Footings poured are covered at night to keep from freezing.



Tuesday, December 7, 2010

Prepping B for the first slab pour scheduled for Friday morning.

The step-down foundation in B has been poured.


We are almost finished with the interior footings in B.


B interior footings



B exterior footing comming into A area about 30'.





Wednesday, December 1, 2010

Rain

It started raining Mon. around 2pm and did not stop until Tue. night. We are trying to remove all the water we can from the slab area.
The elevator pit is full of water. We are in the process of pumping it out. Luckly we were able to pour the base before the rain came.