Wednesday, November 17, 2010

3" of Rain

We received over 3" of rain on the job site between Sunday night and mid-day Tuesday.
While we are waiting for things to dry out we are tying rebar for footers.

Tuesday afternoon we dewatered the slab and footers the best we could with a 2" pump. Today we are pumping out the last bit of standing water with a smaller utility pump.


Waiting on the building pad to dry out.



Monday, November 15, 2010

Rain

Past 24-hr:Precip: 1.06 in (est.)

Rain showers this evening, becoming a steady, soaking rain overnight with a few rumbles of thunder possible. Low 54F. Winds ESE at 5 to 10 mph. Additional rainfall possibly over one inch.

Concrete poured

North West and South side of B exterior and a few interior footers poured Friday afternoon.




















Wednesday, November 10, 2010

Update

We have started excavating footers in area B.

Exterior footers in area B

Rebar is being installed in footings



Rebar delivery 1 of 2 for area C




Rebar for area A & B delivered




Friday, October 15, 2010

Curb finished for today

Curbing has been completed in the area Gary has asked. Next curb might be two weeks out. Gary will let us know when this will be ready.



Cutting asphalt that was laid before we arrived.


First truck onsite.








Curb completed.


- Posted using BlogPress from my iPad

Massey Curb - layout

Massey Curb has four people on site and concrete will be here at 9am.


Laying out radius points.





Curbing machine and equipment on site.

GC stated that we may have approval to move forward with footings in another week. They are waiting on a foundation permit.

- Posted using BlogPress from my iPad

Massey Curb Attended OCIP Training

Massey Curb and four workers from his crew and Ross received OCIP training.


- Posted using BlogPress from my iPad