18 yards of concrete poured in C footings today. All of the footings in area C's first slab pour have been installed.
Slab A is finished, control joints have been cut and curing compound has been applied .
Tuesday, January 4, 2011
266 yards poured today
Slab A poured this morning. 212 yards total
Filling interior grade beams on the A slab.
54 yards poured on the footings for the 1st pour section of C.