Monday, November 29, 2010

13yrds of concrete poured today.

We were able to open up and pour 13 yards of concrete today before the rain hit us at 2pm.
All the footings for the first planned slab pour in area B are now in.









Tuesday, November 23, 2010

B interior

All of the footers that were opened up were poured before the rain started about 11:30 today










Interior Footings of B & eleveator pit

Interior footings in area B excavated
B interior



B interior



Elevator pit foundation was poured this morning.




Steel for elevator pit




Friday, November 19, 2010

B Footings

After all the rain in the begining of the week we were finally able to dig footings and pour concrete in section B














Wednesday, November 17, 2010

3" of Rain

We received over 3" of rain on the job site between Sunday night and mid-day Tuesday.
While we are waiting for things to dry out we are tying rebar for footers.

Tuesday afternoon we dewatered the slab and footers the best we could with a 2" pump. Today we are pumping out the last bit of standing water with a smaller utility pump.


Waiting on the building pad to dry out.



Monday, November 15, 2010

Rain

Past 24-hr:Precip: 1.06 in (est.)

Rain showers this evening, becoming a steady, soaking rain overnight with a few rumbles of thunder possible. Low 54F. Winds ESE at 5 to 10 mph. Additional rainfall possibly over one inch.

Concrete poured

North West and South side of B exterior and a few interior footers poured Friday afternoon.




















Wednesday, November 10, 2010

Update

We have started excavating footers in area B.

Exterior footers in area B

Rebar is being installed in footings



Rebar delivery 1 of 2 for area C




Rebar for area A & B delivered